References
Below is the list of major projects of PBG Oil and Gas and AL Watanyiah United Engineering and Contracting Co.
- Project name:
- LMG Sour Crude Oil Gas Processing Plant.
- Contract type:
- EPC
- Value (USD):
- 550 MM
- Time:
- 08.2008 – 04.2013
Description
Engineering, procurement, construction and start-up of:
- Fourteen (14) wellsites (well facilities/group center)
- Pipelines (gathering and fuel gas pipelines)
- Inlet manifold, HP & LP separation units
- Crude oil stabilization units
- Crude oil desalting units
- Amine H2S removal unit
- Sulfur recovery unit (Euroclaus)
- Low temperature separation and gas dehydration units
- Propane refrigeration unit
- Liquid hydrocarbons fractionation unit (LPG and C5+)
- Power plant
- Electrical, control systems, civil works, etc.
- Project name:
- Nitrogen Rejection Unit
- Contract type:
- EPC
- Value (USD):
- 55 MM
- Time:
- 08.2006 – 11.2010
Description
Erection of basic facilities:
- mercury removal system,
- carbon dioxide removal system,
- system of moisture removal from gas,
- heavy hydrocarbons removal system,
- nitrogen removal unit (NRU) with helium condensate recovery,
- liquid methane pumping system,
- helium condensate compression system, helium condensate warehouse,
- LNG warehouse,
- natural gas compression system with a cooling system,
- internal pipelines system,
- process waste collection system,
- water demineralization system,
- heating system,
- power supply connection with a transformer station,
- internal electric power network with a power generator,
- heating gas system (reduction station + network),
- instrument and measuring air system,
- through nitrogen system,
- exhaust system with flare,
- safety system,
- electronic security system for access to installations and facilities,
- control and measuring system, fully integrated with the control system of the existing Grodzisk Gas Mixing Plant,
- administrative and welfare buildings,
- adjustment of the existing warehouse building for purposes of a spare parts warehouse, traffic maintenance workshop of the nitrogen rejection plant, service rooms,
- warehouse and lubricants building,
- guards building,
- other facilities and installations necessary for the proper functioning of the Investment.
- Erection of auxiliary facilities:
- medium voltage and low voltage electric power cabling network,
- spare electric power supply system,
- lighting of the area,
- lightning and ground protection installation,
- telecommunication network (including fiber optic cables),
- cathodic protection of pipelines,
- sanitary sewage system with a holding tank,
- storm water collection and disposal system (storm water sewerage system),
- water mains system,
- heating system,
- firefighting water tank, pumping station and network,
- sewage holding tank and other
- Project name:
- Wierzchowice Underground Gas Storage, Phase I
- Contract type:
- EPC
- Value (USD):
- 350 MM
- Time:
- 11.2008 – 12.2012
Description
Engineering, procurement, construction and start-up of:
- Inlet filters
- Compressor units
- Thirteen (13) flow regulation and wells development units
- Glycol gas dehydration and regeneration units
- Turboexpander unit
- Fiscal metering units
- Fuel gas station
- Combined cycle power plant
- Heat exchanger units
- Methanol and biocide injection unit
- Liquid nitrogen unit
- Electrical, control systems, civil works, etc.
- Project name:
- Natural Gas Plant “Kościan” Phase I & II
- Contract type:
- EPC
- Value (USD):
- 30 MM
- Time:
- 06.2001 – 12.2002
Description
Construction of 15 Wellsites & Central Facility:
- technical systems:
- slug catchers: 100,000 m3/h
- dehydration TEG: 100,000 m3/h
- dehydration DEG: 100,000 m3/h
- mercury removal: 3×50,000 m3/h
- commercial gas metering system type U3 of 200.000 m3/h
- high-temperature technical boiler house of 300ºC maximum working
- flare for flash gas burning of 16 m height and 100.000 m3/h capacity.
- control and measuring instrumentation including PLC,
- wiring systems such as: 12 power supplies, 6 medium voltage transformer stations,
- fire protection and gas detection system,
- construction of gas pipelines:
- 10”, 100 Bar pipeline length: 14.9km
- construction of glycol pipelines:
- 4”, 220 Bar pipeline length: 17.6km
- 2”, 100 Bar pipeline length: 17.6km
- construction of water pipelines:
- o 12”, 100 Bar pipeline length: 14.9km
- Project name:
- Construction of two shelled diesel oil storage tanks, capacity of 10,000m3 each, and two shelled petroleum storage tanks with floating
roofs, 10,000m3 each, with auxiliary infrastructure at Fuel Storage Base No. 4 at Rejowiec Poznański, Poland
- Contract type:
- EPC
- Value (USD):
- 12 MM
- Time:
- 05.2007 – 06.2008
Description
Development of tank capacity of Fuel Storage Base No. 4 at Rejowiec Poznański:
- site preparation and backup facility organization, demolition, removal of utility clashes, temporary installations, ground leveling,
- removal of clashing utilities,
- construction of new storage tanks 2x10000m3 each with permanently-fixed roofs and storage tanks 2x10000m3 each with floating roofs (foundations, dewatering of excavations, tanks construction, assembly and external and internal welding of bottom, assembly of tank equipment and fittings, platforms and anticorrosion protection)
- construction of process pipelines (supports for pipelines, process pipelines construction, steel bridges and anticorrosion protection),
- waste water infrastructure,
- upgrading of fire-fighting network (construction of fire-fighting installation, division stands),
- electric works and Control and Measurement Apparatuses and Automatics (electric and telephone network, connection of tanks to the existing automation and visualization systems, starting up of Telbud and Entis Pro systems),
- land survey,
- water trials, acceptance procedures by relevant authorities,
- technical acceptance,
- startup and as-built documentation, usage and servicing manuals,
- official usage permit.
- Project name:
- Construction of Yanqul-Fida-Dank Road
- Client:
- Ministry of Transport & Communication
- Contract type:
- EPC
- Value (USD):
- 63 MM
- Time:
- 05.2012
Description
31 km road, made in one of the difficult terrains of Oman.
- Project name:
- Airport base at Musannah – Construction Works
- Client:
- Ministry of Defence
- Contract type:
- EPC
- Value (USD):
- 50 MM
- Time:
- 03.2011
Description
Airport project done including Hangers, Apron, Taxiway, Lighting, Pavements
- Project name:
- Construction of a Hotel City Seasons at Al Khuwair
- Client:
- Sheikh Musallam bin Ham
- Contract type:
- EPC
- Value (USD):
- 42 MM
- Time:
- 03.2011
Description
Hotel City Seasons is one of the leading hotel in Oman
- Project name:
- Construction of Asphalt Road to Wadi Al Sahtan (Wilayat of Rustaq)
- Client:
- Ministry of Transport and Communication
- Contract type:
- EPC
- Value (USD):
- 64 MM
- Time:
- 02.2015
Description
It is a 33 Km of Road to be made in a very tough and challenging terrain
- Project name:
- Upgrading of Sohar Roundabout
- Client:
- Ministry of Transport and Communication
- Contract type:
- EPC
- Value (USD):
- 64 MM
- Time:
- 03.2015
Description
To make flyovers and expansion and modernization of existing roads
- Project name:
- A’ Sharqiyah University Phase -2 at Ibra
- Client:
- A’Sharqiyah Investment Co. SAOG
- Contract type:
- EPC
- Value (USD):
- 60 MM
- Time:
- 06.2015
Description
Making of a new University at Ibra, which is about 180 km from Muscat
- Project name:
- Al Amerat Waste Water Project, Contract A2 – Sewer & Treatment Effluent Pipelines, Al Amerat Western Area
- Client:
- A’Sharqiyah Investment Co. SAOG
- Contract type:
- Joint Venture Partner
- Value (USD):
- 75 MM
- Time:
- 08.2016
Description
Sewerage pipeline network in Al Amerat Western area